Construction report: Riverdale on track for August completion; district outlines multiple active rebuilds and planned COP financing
Summary
Construction services reported March change orders and provided a bimonthly update: Riverdale High School substantial completion targeted for August, Bayshore expansion design due in June, Hector Cafferata K‑8 progressing and Cypress Lake demolition nearing completion. Staff detailed executed change orders and contingency adjustments for March.
Construction services staff presented the required March change‑order report and a bimonthly project update, listing executed change orders, contingency adjustments and the schedule for major projects across the district.
For March, staff reported direct material change orders totaling $957,066.68 (with $54,003.38 returned to the district as project savings), non‑direct contract change orders totaling $51,703.18 (returned to the district as unused funds), and contingency adjustments of $469,962.90. The cover sheet identified two DMP change orders (Edgewood Academy HVAC, Spring Creek Elementary…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat