Commissioners approve change orders for Community Services Building renovations

3204328 · May 7, 2025

Summary

The board approved two change orders — roughly $9,366 and $45,173 — for additional drainage, HVAC brackets, sprinkler heads and drywall/painting tied to rainwater relocation and Second Floor wall moves at the Community Services Building.

Centre County commissioners on Tuesday approved two change orders for the Community Services Building, county staff said, and the project remains within the overall budget so far.

Jonathan (county facilities staff) asked the board to approve a change order with Ainsworth Inc. for $9,365.86 to add drain lines to a water feature, install wall brackets for two condensing units and add sprinkler heads to meet code. He also requested approval of a $45,173 change order with GM McCrossan for added ceiling bulkheads, drywall and painting related to rainwater relocation after some Second Floor walls were moved.

Why it matters: county staff said the Community Services Building includes portions that are roughly 90 years old and that major renovations can reveal unexpected conditions. Commissioners noted the project is still under budget on change orders to date.

The board approved the items by voice vote. Staff said the changes followed necessary code and construction sequencing; no further action was taken at the meeting beyond the approvals.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source