Hendry County School Board gets progress update on new LaBelle High School site and schedule
Summary
District staff reported that 60% construction plans are due soon, subcontractor site visits are planned in May, groundwork is targeted for late July and numerous vendor RFPs will follow as the new LaBelle High School moves into procurement and construction phases.
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
District staff updated the Hendry County School Board on progress for the new LaBelle High School project and warned trustees to expect many construction‑related approvals over the next 12–18 months.
Staff said the project is moving from design into procurement. The architect is due to deliver 60% plans and the district expects subcontractors to be invited to a site visit in May. Staff said groundwork — utilities, grading and drainage — is targeted to begin in late July; once earthwork is underway the district expects to see visible above‑ground progress within 6–9 months.
Officials explained that as the project reaches procurement milestones there will be frequent agenda items asking for approvals of contractors, materials and change orders. “Over the next 18 months, you’re gonna see it really ramping up,” a district official said, adding that staff may call additional meetings and more frequent finance sections on board agendas to handle time‑sensitive purchases.
Staff also said a vendor QR code and sign‑up list will be published on the district website to notify potential subcontractors of bidding opportunities. The administration said it will use an RFP process for subcontractors once 60% plans are complete and that most earthwork and site‑work bids will be among the first procurement steps.
What was discussed: schedule and procurement process for the new LaBelle High School, expected timing for 60% plans, May site visits, late‑July groundwork and the possibility of more frequent board approvals as the build progresses.
What was decided: no board vote on contractors or sites at the meeting; the report was informational and staff will bring procurement items forward as bids are ready.