The Anacortes City Council on May 5 authorized a $131,648 contract with Raw Land Construction to replace eight water service lines and saddles on the South Commercial Corridor before planned paving; work will be done at night to limit business disruption.

Anacortes City Council on May 5 authorized the mayor to sign contract 25-119-WTR-001 with Raw Land Construction LLC for $131,648 to replace selected water services on the South Commercial Corridor ahead of a planned paving project.

The contract covers replacement of eight service connections and the associated saddles that attach service lines to the city’s main, according to Andy Rayum, Public Works Director. Rayum said staff identified a subset of service lines most likely to fail and that "we're proposing to do the service replacements at night" to avoid disrupting businesses in the corridor.

The move follows concerns raised at a prior meeting about tearing up newly paved roadway if service lines fail after repaving. Councilmember Walters said the committee reviewed the mains and services and noted the main in parts of the corridor is an older, 1940s-era asbestos-cement pipe that appears to have a thicker wall than other pipes in town; that, combined with replacing problem saddles, "makes me feel quite a bit better" about the line's risk of failure. Rayum also said most of the identified services are 3/4 inch; one is a 2-inch service serving Bubba's Eds.

Councilmember Young moved the contract; Councilmember Walters seconded. The roll call vote recorded in the meeting was: Young — yes; Walters — yes; Clelia McGrath — yes; Moulton — yes; McDougal — yes; Cevic — yes; Fantini — yes. The motion carried.

Discussion vs. decision: Council discussion focused on risk reduction before paving, customer and business impact from daytime repairs, and the adequacy of replacing selected saddles rather than wholesale main replacement. The formal action was the authorization of the contract; staff will schedule the work and proceed with nighttime replacements as described.

Background and next steps: The replacements are timed to precede scheduled South Commercial paving later this year. Rayum said the work will give crews additional opportunity to observe main condition along the corridor. The contract award initiates construction coordination and scheduling with businesses for nighttime access. No amendments to the contract were proposed at the meeting.