The Lincoln County Board of Commissioners on May 5 accepted a bid from Shelco Construction to perform asphalt overlay work in three subdivisions, awarding the Lincoln County Department of Roads 2025-02 project for a bid total of $671,440.
Deputy Highway Superintendent Brian Glass (packet presenter) told the board the bid covered 6,160 road tons at $109 per road ton, with a project start date in July and a projected completion date in August; the highway staff recommended Shelco based on the earlier completion window compared with a competing bid that matched the price.
Why it matters: The project will resurface roads in Fairway Estates, Calvary Hills (north) and Prairie View Acres West, improving roadway conditions for residents and reducing long-term maintenance needs.
What the board did: Commissioners accepted Shelco Construction's bid and approved the project to begin July 21, 2025. The motion passed by roll call.
Next steps: Highway staff will coordinate schedules with the contractor and return to the board if any material changes are needed; the county thanked both bidders for competitive submissions.