Court approves IGMP #2 addendum as jail conversion work advances; GMP projected at $55.5–$56.5 million
Summary
McLennan County commissioners approved an addendum April 28 that lets the construction manager order long‑lead materials and subcontract work under Interim Guaranteed Maximum Price package No. 2 for the downtown jail‑to‑courthouse conversion.
McLennan County commissioners on April 28 approved an addendum to the county’s construction manager‑at‑risk agreement to allow work covered by Interim Guaranteed Maximum Price (IGMP) proposal package No. 2 to proceed, the court heard during a construction progress update on the courthouse conversion project.
The county’s construction representative told the court the official first day of work on the project was Feb. 24, 2025, and that selective demolition, mechanical‑electrical‑plumbing removals and surface blasting are complete in many areas. “Our official first day of work on the project was 02/24/2025,” the presenter said. He said crews have cleaned concrete surfaces in preparation for fiber‑reinforced polymer (FRP) wrapping, and that the FRP subcontractor was scheduled to mobilize the following Monday.
Why it matters: the court was…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat