Shippensburg Area SD reports construction progress; district monitors stadium track settling

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District facilities staff reported progress on middle- and high-school construction — including sidewalks, a revised water meter vault, and structural steel delivery — and said K&W and contractor ECI are addressing a settling issue at the new high school track. A single electrician change order was approved; contingency figures were discussed.

Shippensburg Area School District facilities staff reported ongoing progress on middle- and high-school construction and said contractors are evaluating a settling problem at the new high school track that has halted final track work.

Jason, facilities staff, told the Facilities Committee that site work and building components are moving forward: concrete, masonry and structural steel are on site, the district has been invoiced for about 24 percent of the work, and sidewalk requirements set by Shippensburg Borough have been resolved and are being installed. He said a shop drawing for a water meter vault returned from the borough with design changes, including a required bypass around the meter, and that the district is negotiating pricing with the general contractor for that work.

The scoreboard at the high school stadium has been installed, Jason said, and electrical tie-ins and coordination of the stadium play clocks with the scoreboard manufacturer are in progress. Track painting is on hold until nighttime lows stay at or above 50 degrees and until the settling issue is resolved.

Committee members and staff discussed a span of the new track that has settled. Fred, a school board member, asked whether the district would be responsible for repair costs; Jason said, "At this point, no," and added that K&W (the designer) and ECI (the general contractor) have been asked to evaluate and address the area. Jason said the district has involved K&W and ECI, tapped SiteLogic personnel to help coordinate, and consulted the district attorney to ensure proper handling of liabilities and repairs.

On project finances, Jason reported one approved change order for electrical work tied to code revisions discovered during the building permit drawing review by the township. He also reported contingency figures discussed at the meeting: "the original contingency was about 275,005.50, and we're about 244,421 at this point," as stated in the meeting record.

The district emphasized that the settling needs investigation before the track can receive its top coat and before painting resumes. Jason said geotechnical borings exist for the project but not at every square foot of the track; the team is reviewing boring records to determine whether the specific settled area was tested and will have K&W and ECI perform an evaluation and a plan for repair.

No formal motion on contractor liability or contract changes was recorded during the discussion; the committee heard updates and directed staff to continue coordinating with K&W, ECI and SiteLogic and to report back.

Background: contractors and firms named in the discussion include K&W (designer), ECI (general contractor), SiteLogic (coordination support), Mid State Electrical (subcontractor), and UGI (gas main relocation agreement referenced for the parent drop-off loop).