Commissioners award two public‑works contracts; FEMA funds part of culvert work

3155168 · April 29, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Cowlitz County Board of Commissioners awarded bids for the Italian Creek culvert replacement and the Delameter Creek (Garlock Road) fish‑passage project; both votes passed and staff said the Italian Creek award is more than $100,000 under estimate while the Garlock Road award exceeded the engineer's estimate due to concrete costs.

Cowlitz County commissioners approved two public‑works bid awards Wednesday: a culvert replacement on Town Creek Road and a fish‑passage replacement on Garlock Road (Delameter Creek).

County Engineer Susan Eugenis told the board item 7 — the Italian Creek culvert replacement on Town Creek Road at milepost 1.9 — is a FEMA‑funded project to replace a culvert damaged in a storm. The county received seven bids; the apparent low bidder withdrew and the county identified DeWitt Construction as the lowest responsible bidder at $434,355. Eugenis said that amount is “over a hundred thousand dollars below the engineer's estimate.”

Item 8 — the Garlock Road/Delameter Creek fish‑passage project — will replace an existing box culvert with a 55‑foot span steel arch culvert. Staff received seven bids; the successful bidder was Western United Civil Construction at $2,349,120. Eugenis told commissioners the final price exceeded the engineer's estimate largely because of higher concrete foundation costs.

Board action: A commissioner moved to approve item 7; the motion passed by voice vote (ayes recorded). The board then moved to approve item 8; that motion also passed by voice vote. Staff said the Italian Creek design is about 75% complete and, assuming permitting proceeds, the project would go out to bid this fall for construction; the temporary bridge in the Pleasant Hill Road area is a county‑owned structure placed to reopen a roadway while final work proceeds, staff said.

Why it matters: The Italian Creek replacement repairs storm damage under a FEMA program. The Garlock Road project replaces a barrier to fish passage with a larger span structure intended to restore fish mobility in Delameter Creek; staff said Delameter Creek is a documented fish stream that supports at least two salmonid species.

Ending: Commissioners approved both contracts and moved to the next items on the agenda.