Mayor: Pinewood EMS station renovation on track; animal shelter geotech work underway
Summary
The county mayor reported the Pinewood EMS station plans have state fire marshal approval and renovation work is underway with an expected June station readiness; geotechnical work for an animal shelter and interviews for a planning-and-zoning director were also announced.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
County leadership reported progress on county facilities and staffing at the April 28 meeting.
County Mayor reported that the Tennessee State Fire Marshal stamped plans for the new Pinewood EMS station and that renovation work is underway; doors have been ordered and the county’s project manager is confident an ambulance can operate from the station in June. "We're pretty confident that we're going to have an ambulance in that station June," the mayor said, noting construction is a design-build project and some design adjustments remain possible.
On animal-welfare infrastructure, the mayor said geotechnical work is under way at the preferred animal-shelter site and that utilities are available on the proposed side of the road so crews will not need to bore under the road. He also reported the park light-pole that storm-damaged has been replaced and is operational.
The mayor told commissioners he circulated a suggestion to name a county building the "Edwin Hickman Memorial Building" and requested feedback; one commissioner replied by email, the mayor said. Separately, interviews are scheduled Friday morning for the planning-and-zoning director position.
Why it matters: The EMS and shelter updates signal near-term changes in county emergency response capacity and animal services; the planning-and-zoning hire and a proposed building name are administrative items with local community visibility.
What’s next: Staff will continue renovation and site work; the mayor and project manager will report on schedule and permit milestones. Planning-and-zoning director interviews are scheduled and the commission will receive candidate information for a separate appointment process.