CHA reports construction, permitting progress and phased schedule for North Penn High School
Summary
CHA consultants told the Facilities and Operations Committee that phase 1 work is under way, phase 2 bid packages will be advertised in late May, and permitting and utility coordination are advancing; the project remains on the July 2024 budget baseline the team presented.
Consultants from CHA updated the North Penn Facilities and Operations Committee on April 28 about progress on the North Penn High School renovation and addition, saying permitting, early procurement and phasing are advancing and that the project remains on the budget baseline discussed in July 2024.
Michael Lynch, a CHA representative, told the committee the team has resubmitted land-development materials for the planning commission and expects planning and supervisor reviews to continue through the late spring and early summer. He said the team has cleared many zoning concerns, coordinated with PECO on electrical and gas procurement and reached an agreement with the North Penn Water Authority to convey water lines on district property to the district to allow necessary modifications.
Lynch said both phase-1 and phase-2 NPDES permit applications have been submitted; phase 1 has received…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat