Engineer updates: Broadhead sewer, C20 separation, public‑works building and street paving schedule

3126959 · April 25, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Borough engineer reported on Broadhead sewer bidding, C20 sewer separation work, a public‑works building bid opening, Steuben‑Linden intersection signal work and brick/road paving timetables; council asked about detours and resident notification.

Borough Engineer Larry Keenan told council several infrastructure projects are moving forward and provided dates and scope updates.

Broadhead Sewer Project: Keenan said bid documents are finalized and that bids will be brought to council after closing; council anticipated possible approval in June.

Ewing Road alternative analysis: The infrastructure committee is still reviewing cost options and drainage and grading elements. Committee members asked that the initial estimates be shared with the finance committee for early review of fiscal impacts.

C20 Sewer Separation: Field work is under way with construction beginning at Duncan Avenue near Maxwell and progressing toward Steuben Street; PA American Water is relocating waterlines as needed. Keenan said the project will affect Steuben, Linden and Duncan and that completion remains projected for November. He said traffic-control plans and specific detour information will be provided as the work approaches busier segments.

Public Works Building: The public‑works building project is out to bid; bid opening was scheduled for May 15 and council will have 60 days after bid opening to accept a bid.

Steuben‑Linden intersection improvements: New signal poles and arms are being delivered and installed; two adjacent trees on Steuben will be removed prior to signal arm placement. Keenan said that the intersection work is expected to be done before the C20 sewer work reaches that point.

Road paving and brick restoration: Keenan reviewed the 2025 paving program and the Broadhead sewer-related paving sequence. He said milling occurred and final paving was scheduled for a late‑May date but that weather may require postponement. The engineer said social media notices and contractor resident notifications will be used to alert affected streets; council asked for advance notice so residents can move vehicles before paving.

People’s Gas and Liberty Fuel: Keenan reported paving restoration work related to gas main activity and said Liberty Fuel Supply will complete final restoration at 1967 Grafton Boulevard next week.

Why this matters: The projects affect traffic patterns, parking access and utilities for residents on the named streets; council members pressed for clear advance notice on detours and final paving dates to avoid one‑day surprises.

What happens next: Keenan and staff will provide traffic‑control plans and timetables as work approaches busy corridors and will circulate cost details from the Ewing Road alternative analysis to finance committee members.