District approves change order and demolition as kindergarten center construction continues

3122542 · April 25, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Glen Ellyn SD 41 staff reported additional low‑voltage scope and site work for the kindergarten center; the board authorized an approximately $275,000 change order and approved demolition of two acquired houses for $46,935.

District staff told the Board on Oct. 21 that the kindergarten center construction is progressing and that additional low‑voltage scope (door access and related safety devices) was discovered after contract award. The board authorized Assistant Superintendent Eric De Porter to execute an approximately $250,000–$275,000 change order to bring that work into specification and on schedule.

Eric De Porter described the change order as necessary because the originally bid low‑voltage scope did not fully match the district’s existing building specifications for safety devices and access systems; staff said the cost is within the master project budget but exceeds the superintendent’s delegated change‑order authority, so it required board approval.

The board also approved demolition of two district‑owned houses acquired for the project — listed in the meeting materials as 1 N 221 and 1 N 249 Bloomingdale Road — awarding the demolition work to Upright Construction for $46,935. Staff told the board this was the low bid and a contractor the district has used previously.

Board members noted the demolition and change order are time sensitive because devices must be ordered and site work scheduled to match the project timeline. Both authorizations passed on roll‑call votes.