Council approves $19,500 change order to deepen Lift Station Site C for sewer project

3117578 · April 25, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved a $19,500 change order to increase the depth of Lift Station Site C by about 1.5 feet to reduce flood risk; staff said the work will increase capacity and prevent potential overflow to a nearby creek.

The Bruceville-Eddy City Council approved a change order for SJ and J Construction, LLC, to increase the depth of Lift Station Site C by about 1.5 feet at a cost of $19,500, a measure engineers said is intended to reduce flood risk and increase wastewater capacity.

Staff and the project engineer reported that, during bidding and site inspection, the lift-station location was found to have higher-than-anticipated drainage risk from nearby creekflow and vegetation. The engineer recommended lengthening the lift-station structure to provide additional capacity and prevent overflows into the creek.

Project drawings presented at the meeting showed the extension from roughly 11 feet to 13.3 feet in a key dimension; Taber Associates and city staff recommended approval of the extra work and cost. A motion to accept the change order passed unanimously after Councilman Prater seconded.

City staff said the change order is part of the ongoing sewer construction contract and will be processed through standard contract change controls; the vendor SJ and J Construction, LLC will perform the additional excavation and installation work under the same project contract.