Public Works presented plans to reconfigure and expand the Waste & Recovery Center to increase capacity and safety; commissioners authorized a request for qualifications for owner advisory and construction services as the county pursues a design-build delivery to deliver an estimated $20 million project.
Get email alerts on the Solid Waste Capital Project topic
No spam. Unsubscribe anytime.
Thurston County Public Works briefed commissioners on plans to reconfigure and expand the county's Waste & Recovery Center and authorized staff to issue a request for qualifications for owner advisory and construction services.
Public Works Director Erin Weese and Solid Waste Manager Jeff Bickford described a design-build approach for a project the county estimates will cost about $20 million. The reconfiguration aims to expand capacity, separate residential and commercial traffic to improve safety, reduce customer queue times, and lower long-term maintenance and operational costs.
County staff said the project is complex because the facility must remain operational during construction. The design-build delivery method was selected to provide a single design-build entity responsible for both design and construction and to improve coordination. The county expects to select an owner-advisory/constructability consultant under the RFQ for an estimated three-year contract of about $600,000; the negotiated contract will return to the board for approval.
Public Works described the project timeline: RFQ responses for owner advisory in 2025 with selection by July 2025, a subsequent RFQ/RFP for the design-build contractor and project review committee submittal later in 2025, and expected construction in mid-2026 through 2027. Commissioners requested a public briefing work session to provide an overview and broader public engagement; staff agreed to schedule a 30โ45 minute session in May and to publish materials to increase transparency.
The solid waste advisory committee has reviewed and supports the design-build approach, staff said.