Council asks staff for lower-cost East State Street option after lengthy public debate over sidewalks and bike lane
Summary
Montpelier's planned East State Street reconstruction touched off a lengthy public discussion Tuesday over sidewalks, a proposed uphill bike lane, utility poles and impacts to front yards and porches.
Get email alerts on the Roads And Transportation topic
No spam. Unsubscribe anytime.
Montpelier's planned East State Street reconstruction touched off a lengthy public discussion Tuesday over sidewalks, bike lanes, utility poles and impacts to front yards and porches.
Public works staff presented three conceptual options and cost estimates: a full build (sidewalks both sides plus an uphill bike lane), a scaled option with a continuous bike lane and targeted new sidewalk segments, and a minimal reconstruction that restores existing walkways and utilities. The presentation listed a full-build estimate of about $9 million and a scaled option near $8.2 million; staff said portions of the project are already funded with an existing bond authorization and USDA grant money.
Why it matters: East State Street connects downtown to the college and serves as a major collector with mixed uses: businesses, multi-unit housing, a bus route and elementary-school access. Residents and councilors said pedestrian safety and winter conditions are priorities; several speakers said the existing narrow south-side sidewalk freezes in shade and becomes unsafe. Others warned that widening to add bike lanes would require retaining walls, move curbs closer to historic porches and could require property impacts.
What the council asked staff to do: Following public comment and questions about right-of-way, pole relocation and cost breakdowns, council directed staff to return with an alternative cost estimate that (a) removes the dedicated uphill bike lane and (b) provides a continuous sidewalk on the north side from Main Street to College Street. Council members said they wanted that specific option costed and returned for final design so they could decide how to prioritize pedestrian safety, bike facilities and budget constraints.
Technical and funding notes from staff: Contract 1, now under construction, separates stormwater from the sewer system and includes a stormwater treatment outfall and associated treatment measures; staff said about $1.1 million of earlier work is tied to stormwater treatment. Staff described a funding package that includes a $7.2 million bond authorization, a $3.5 million USDA grant that can fund either East State or wastewater work, and a $1.2 million ARPA grant applied to the CSO separation. Staff warned that a full-build option would require additional borrowing if the council wishes to proceed immediately.
Next steps: Staff will return with the requested option (no uphill bike lane + continuous north-side sidewalk) and associated cost and design impacts, and the council will consider that option at a future meeting before final design and bidding.