Dalton council approves GDOT extension, manufacturer change and inspection order for airport hangar project

3099444 · April 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

On April 21 Dalton Mayor and Council approved a 12‑month extension to the GDOT hangar funding contract, a manufacturer change order that saves about $105,235 and a $1,991.33 task order for seven‑day inspection services, enabling imminent construction on the airport hangar development project.

Dalton Mayor and Council on April 21 approved a 12‑month extension to the Georgia Department of Transportation (GDOT) funding contract for the city’s airport hangar development project, a manufacturer change order that reduces costs and lead time, and a task order for inspections required during construction.

The extension was presented by Andrew (staff member), who said the city “entered into a funding contract for our hangar development program in June of 2023. That contract will expire June of this year. So GDOT is offering us a 12‑month extension on that funding contract to cover the construction, which is about to begin on that project.” The council approved the extension by motion; a roll‑call tally was not specified on the meeting record.

The council also approved Integrated Builds change order No. 1 on the same project. According to the staff presentation, the change in the T‑hangar manufacturer will save the city $105,235.15 and shorten material lead time by about six months. Council members voted to approve the change order; the meeting record lists the motion and a second but does not include individual vote tallies.

The council approved Croix Engineering task order No. 12 for MPDES seven‑day inspection services at a cost of $1,991.33. Staff said that amount was already included in the hangar budget and that savings from the change order would cover potential future change orders up to $105,000. The motion to approve the inspection task order passed without an individually recorded tally.

Why it matters: the GDOT extension and manufacturer change clear key contractual and scheduling hurdles ahead of construction and reduce near‑term cost risk, while the task order secures required inspection services during work.

The city’s funding contract originally began in June 2023; the extension preserves GDOT funding while the city proceeds to construction. Council members did not debate the merits at length during the meeting and there were no public comments on the item.

Items related to this project were presented consecutively and approved during the April 21 meeting. The items approved were limited to the contract extension, the Integrated Builds change order, and the Croix Engineering inspection task order.