County gives detailed update on White City transmission main, tanks and new well; booster-station work to follow
Summary
County staff reported that the north transmission main has been installed and pressure-tested, foundations for two ground-storage tanks are poured in White City, and a second well north of White City is in procurement with a late-summer installation expected; advertising for booster-station contracts will follow.
County staff provided a project update on the county’s water buildout on April 22, saying key pieces of the north transmission main and storage-tank work are nearly complete and that a second production well is proceeding through permitting and procurement.
Staff said the line from the planned White City treatment plant to the Jones Homestead booster station is installed and has passed pressure testing;…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat