College Place council approves $1.5 million contract amendment for Phase 1B of wastewater plant

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The City Council authorized the city administrator to sign a time-and‑materials contract amendment with JUB Engineers not to exceed $1.5 million for construction management services tied to the wastewater treatment plant Phase 1B project.

The College Place City Council on April 22 authorized the city administrator or designee to sign a contract amendment with JUB Engineers for time-and-materials construction management services for the wastewater treatment plant Phase 1B project, not to exceed $1,500,000.

City Administrator Mike Rizzatello told the council the Phase 1B work includes excavation to create a large storage basin for treated effluent, construction observation, repackaging of bids, and permitting work including dam-safety requirements. He said Phase 1A focused on replacing equipment while Phase 1B will create additional storage capacity prior to creek discharge.

Rizzatello said the project financing is a package that includes a Washington State Department of Ecology grant, sewer lining and lift station work, and congressional-directed spending. He identified a $3.5 million congressional allocation from Representative Cathy McMorris Rodgers as “still in play” and said the broader financing package from Ecology and other sources totals more than $26 million.

Council members asked clarifying questions about cost and funding; no member opposed. A motion to authorize the amendment was seconded by Council Member Williams and approved by voice vote.

The amendment covers construction management services on a time-and-materials basis; the contract will be administered by the city administrator or designee. No vote tally was recorded in the public transcript and no additional conditions on the amendment were reported.