McPherson County approves final closeout and $6,000 drawdown for water district CDBG project

3094870 · April 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commissioners signed final CDBG closeout paperwork and approved a $6,000 final disbursement for a water-line replacement and well work project for McPherson Bridal Water District No. 1, which cost about $1.34 million and received loan forgiveness and a $250,000 grant.

Commissioners for McPherson County on April 21 signed final closeout documents and approved a $6,000 final drawdown on a Community Development Block Grant for McPherson Bridal Water District No. 1.

The project replaced about 2,750 feet of waterline, abandoned an existing line, repaired two wells, built a fluoridation station and constructed a new standpipe, Rosemary Saunders of Ransom Financial Group LLC told the board. “Everything is working accordingly,” Saunders said, adding the district had a closeout meeting in February and that some delays were caused by the field representative’s medical leave.

The total project cost reported to the board was $1,342,500.76. The district received a $250,000 grant and loan forgiveness on other loan amounts after the work brought two previously separate systems into a single compliant system, Saunders said. Commissioners approved the chairman signing the closeout paperwork and the final $6,000 disbursement.

County staff said they will deliver signed documents to the state and reconcile the exact drawdown amounts before submission.

Background: The work described restores compliance for the district’s water system by unifying two operating systems into one, the consultant said. Commissioners and the consultant discussed a planned phase 2 and phase 3 of improvements, with similar funding approaches anticipated.

Votes at a glance: The board approved the chairman signing final CDBG closeout documentation and authorized the final $6,000 disbursement; motion carried by voice vote.

Ending: Saunders said the district was pleased with the finished work and that phase 2 will extend some waterline into town, replace valves and meters and continue efforts to reduce water loss.