Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Rear Main project faces two‑ to three‑month preconstruction remedial work before main contract resumes
Summary
Director Stevens said contractors and engineers are mapping underground structures, addressing unsuitable soils and high groundwater, and preparing change orders. Staff estimated 2–2.5 months of additional remediation before the original contract work can begin.
Director Stevens updated the committee on the Rear Main project, describing ongoing geotechnical and utility investigations and preparatory work required before the original construction contract resumes.
Stevens said staff are coordinating with engineering firm Fuss & O'Neil, contractor UEL and the city engineer to map the limits of Pond Brook through the site and to verify whether concrete footings will be affected. He said Fuss & O'Neil is preparing an…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat

