Committee accepts revised WPS easement route for Garfield Avenue at Marathon Park
Summary
Marathon County approved a revised Wisconsin Public Service (WPS) easement that reroutes lower-pressure gas service across green space south of the splash pad to avoid a high-pressure line and limit conflicts with future park uses.
Get email alerts on the Utility Easement topic
No spam. Unsubscribe anytime.
The committee accepted a revised easement from Wisconsin Public Service to relocate gas service lines at Marathon Park.
Staff explained the revised route moves service away from a high-pressure line that previously ran in an alley between park buildings. The proposed new alignment largely crosses green space south of the junction building and north of the splash pad; the lower-pressure route terminates south of the splash pad and will allow future branching for any structures that need gas service without encountering the previous high-pressure constraints. Parks staff reviewed the alignment and reported no anticipated conflicts with foreseeable park uses. The committee approved the revised easement by voice vote.