Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Board approves $67,009 in All Seasons Arena change orders; contingency remains
Summary
The county approved three change orders totaling $67,009.36 for All Seasons Arena construction work; contingency funds remain in the project budget and the change orders will be divided among the facility partners per the joint powers agreement.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Blue Earth County approved three construction change orders April 22 for the All Seasons Arena totaling $67,009.36.
County staff reported the change orders include a Met Con change order for $11,338.88 for a photo eye, lighting and mezzanine structural improvements; a $40,000 change order to Rink Tech to address substructure aggregate under the rink floor discovered during flooring removal; and a $15,670.48 electrical change order to Laketown Electric for additional arena electrical work. Staff said those amounts leave a project contingency of roughly $169,000 remaining.
The All Seasons Arena Board previously approved the change orders; because the arena is a joint powers project, the partners also needed to approve them at their respective governing bodies. County staff said the costs will be divided among the three partners according to previously agreed percentages in the construction budget. The board moved and approved the change orders by voice vote.

