Sarpy County selects Hawkins Construction for Southern Sarpy Expressway pre-construction services

3090653 · April 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Sarpy County Board of Commissioners approved a $400,000 pre-construction services agreement with Hawkins Construction to serve as construction manager/general contractor for the Connect Sarpy Southern Sarpy Expressway project; the board discussed timeline acceleration and next steps.

Sarpy County commissioners voted April 22 to hire Hawkins Construction Company as the construction manager/general contractor (CMGC) for the Connect Sarpy Southern Sarpy Expressway and approved a $400,000 pre-construction services agreement to move the project toward design and potential 2025 construction.

County deputy administrator Scott Bovec told the board the selection committee reviewed four proposals, conducted interviews and recommended Hawkins based on schedule confidence, budget alignment and the lowest CMGC multiplier among respondents. The pre-construction agreement funds collaboration between the CMGC and the engineering firm to refine phasing, pricing and efficiencies during design.

The board discussed the project as a large, multi-year infrastructure undertaking. Commissioners and staff said there is an opportunity to accelerate the schedule: the selection committee and Hawkins indicated the work could finish about a year sooner than earlier projections, which raised optimism about starting construction this year.

The board approved the motion to select Hawkins for pre-construction services; the motion was made by Commissioner Warren and seconded by Commissioner Kelly. The clerk recorded the tally as four ayes, with Commissioner Mixon absent, and the motion carried.

County staff present for the item included Scott Bovec and County Engineer Denny Wilson; Luke Ritter of Hawkins Construction was introduced as the project manager, and HDR staff were identified as the engineering partner. Staff said the CMGC will participate in design meetings to identify constructability improvements and pricing efficiencies before the county seeks final contract authorization.

The board’s remarks placed the Southern Sarpy Expressway in the context of broader county transportation efforts that commissioners said have reshaped county travel patterns in recent years. Commissioners asked staff to continue reporting schedule, budgeting and design milestones back to the board as the pre-construction phase progresses.

Votes and formal action recorded on the item are limited to approval of the $400,000 CMGC pre-construction agreement; staff said further contract approvals and project phases will return to the board for subsequent votes.