Facilities committee reports 49 bond projects under way; district sets May 28 completion target for Aquatics Learning Center
Summary
The Boerne ISD Facilities Committee reported on April 21 that 49 projects tied to the 2022 bond are underway (23 completed so far). The district said contractor engagement and daily site visits continue at the Aquatics Learning Center and established a May 28 final completion deadline for the pool.
Boerne ISD's Facilities Committee provided a progress report at the April 21 board meeting on bond-related projects and capital work across the district.
Committee report and status Trustee Carlin Fryer summarized the Facilities Committee's work: architects are finalizing elementary-level educational specifications and will move next to secondary campuses; technical specifications for construction standards will be prepared. The committee reported 49 projects related to the 2022…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat