Construction on county mental‑health facility remains on schedule for summer turnover, contractor says

3086850 · April 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

BW Construction reported that the 120‑bed mental‑health facility’s contract remains at roughly $7.996 million, with substantial completion expected by July 3 and final turnover paperwork by Aug. 18, barring permit delays.

BW Construction project manager Mark Manship gave commissioners a detailed construction progress update on the county’s mental‑health facility during the April 21 meeting.

Manship said the contract value remains $7,996,017 and that only a no‑cost time extension change order has been approved so far. He reported steady progress on exterior and interior work and said substantial completion is targeted around July 3; the project’s administrative completion date is projected Aug. 18.

Why it matter…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans