Construction on county mental‑health facility remains on schedule for summer turnover, contractor says
Summary
BW Construction reported that the 120‑bed mental‑health facility’s contract remains at roughly $7.996 million, with substantial completion expected by July 3 and final turnover paperwork by Aug. 18, barring permit delays.
Get email alerts on the Capital Projects Construction topic
No spam. Unsubscribe anytime.
BW Construction project manager Mark Manship gave commissioners a detailed construction progress update on the county’s mental‑health facility during the April 21 meeting.
Manship said the contract value remains $7,996,017 and that only a no‑cost time extension change order has been approved so far. He reported steady progress on exterior and interior work and said substantial completion is targeted around July 3; the project’s administrative completion date is projected Aug. 18.
Why it matters: The facility is a county capital project with a multi‑million‑dollar contract, and officials said timely completion is needed to relieve current capacity pressures and to begin moving furniture and equipment in advance of occupancy.
Work completed and outstanding Manship listed recent progress: roofing and nearly all storefront glazing are complete; hardy (fiber‑cement) siding is installed and being painted; sanitary and hydrant taps were completed; detention pond and additional discharge were installed to satisfy updated 100‑year flood requirements; plumbing and electrical rough‑ins are substantially complete; and the generator is on site. The project team reported drywall, finishes and HVAC ductwork in progress and scheduled delivery of furniture and loose equipment to begin around June.
Schedule and risk A March change order extended the contract time to 334 days; Manship said that yields a projected paperwork/turnover completion on Aug. 18 but that substantial construction completion should fall closer to July 3, allowing the county the statutory 30‑ to 38‑day move‑in window. He noted the team has addressed a drainage permitting delay that previously affected the schedule; no other major time‑impacting issues were reported in the update.
Costs and contingencies Manship said only one approved change order so far (time‑only) and that the contract dollar amount remains unchanged. Commissioners asked questions but reported no additional cost approvals at the meeting.