Oestria Solar reports steady construction; contractors found buried drum and two unknown wells
Summary
Oestria Solar (construction update) reported roads and laydown yards installed, erosion controls in place, weekly inspections clear so far, discovery and removal of a buried 55‑gallon drum pending final report, and two previously unknown wells that will be evaluated and likely capped.
Tripp Stachem reported construction progress at the Oestria Solar site and described environmental and safety items found and addressed during work.
"Everything so far is on schedule," Stachem said, noting road construction is over 50% complete, laydown yards are installed and the site entrance is finished. Stachem said best management practices (BMPs) such as silt…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat