Solon City Council approves $201,000 change order to accelerate Solon Road reconstruction
Summary
The Solon City Council voted unanimously at a special meeting to approve change order No. 1 for the Solon Road reconstruction contract (Contract 2018Dot36), adding $201,000 to the contract to fund acceleration measures under the city’s two-lane, one-way maintenance-of-traffic plan.
The Solon City Council voted unanimously at a special meeting to approve change order No. 1 for the Solon Road reconstruction contract (Contract 2018Dot36), adding $201,000 to the contract to fund acceleration measures under the city’s two-lane, one-way maintenance-of-traffic plan. The council approved the change order under emergency procedures to allow construction to start as soon as possible.
The change order bundles several acceleration options — an extra 10‑hour workday, limited Saturday work to meet milestones, nighttime paving and nighttime cement stabilization — that city staff said together total about $201,000. City staff said applying those options in full could shorten the planned 10‑week project to roughly six weeks, weather permitting. Officials also said choosing a two‑way traffic plan instead of the one‑way maintenance plan would increase the schedule by about six weeks and add roughly…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat