Land Bank approves ADA upgrades at Long Pond Landing
Summary
The commission approved changing an accessible gravel parking spot to a concrete surface and installing boardwalks and accessible paths at Long Pond Landing to improve access to the dock and viewing deck.
Get email alerts on the Accessibility topic
No spam. Unsubscribe anytime.
The Nantucket Land Bank Commission voted to approve additional accessibility upgrades at Long Pond Landing, including replacing a gravel accessible parking stall with a concrete pad, installing boardwalks for improved access to the dock and viewing deck, and restoring some crushed-stone areas to grass.
Staff presented design changes after receiving feedback that the existing crushed-stone path, while intended to be accessible, posed practical difficulties for some wheelchair users. The proposed plan reserves a single concrete ADA parking space and places boardwalks in the brown-marked areas shown in the staff design; other parking and crushed-stone areas would remain unchanged or be restored to grass where appropriate.
Commissioners discussed the problem raised by a wheelchair user being pushed by an elderly helper, and staff confirmed that gravel—even when placed in a grid—can be difficult in practice for mobility devices. Commissioner Alan asked whether a washed-aggregate concrete that is used at another Land Bank site could be considered; staff said they would obtain price and specification comparisons.
A motion to accept the upgrades and design changes was made and seconded. Roll call: Commissioner John: Aye; Commissioner Alan: Aye; Commissioner Mark: Aye; Chair: Aye. Tally: 4 yes, 0 no. The motion carried.
Staff said permitting is required for some of these changes and that bidding or in-house work will proceed after budget and permitting steps are confirmed; the work might take until the fall to complete, depending on permitting timelines.
The commission asked staff to check material options (including washed-aggregate concrete) and to proceed with budgeting and procurement steps.