Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Transportation topic

No spam. Unsubscribe anytime.

VDOT outlines secondary six-year plan, Crystal Lake Road start and series of safety projects for Nottoway County

3048670 · April 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Virginia Department of Transportation staff presented a draft secondary six-year plan and multiple district projects including imminent work on Crystal Lake Road, rural-rustic projects on Williamson Road, rumble-strip installations on Route 360, and ADA ramp upgrades in Crewe. The board agreed to send the draft to public hearing on May 15.

A representative from the Virginia Department of Transportation (VDOT) briefed the Nottoway County Board of Supervisors on a draft secondary six-year plan and a slate of near-term construction and safety work on county-maintained roads.

Key items in the draft plan include a fully funded Crystal Lake Road project that VDOT said would begin construction within weeks; rural-rustic projects on Williamson Road that are held up pending a right-of-way study and negotiations with a private landowner; and priority entries for Barnes Lane (funding completion projected FY2028) and Hawthorne Drive (projected FY2031).

The VDOT presenter said the county's telephone-fee (tele-fee) funding balance for secondary projects stood at about $162,000 going into the fiscal year, with an expected accrual of roughly $33,000 per year for each of the six years covered by the plan. In the final year there is only about $11,000 unallocated, and staff did not propose a small project for that amount because typical rural-rustic hard-surface jobs cost significantly more.

VDOT also reported updates on other district projects:

- Route 46 bridge replacement: Concrete pours and pier wall work were on schedule; alternating lane closures were planned to begin April 28 and contractor mobilization would occur the following week. - ADA sidewalks in Crewe: Intersection ramp upgrades for Americans with Disabilities Act (ADA) compliance were planned along U.S. 460 and on Carolina Avenue. - Systemic unsignalized intersection safety study: The district recommended warning signage and other modest countermeasures at the Spainville Road/Old Richmond Road intersection and the Turkey Island Road/Cellar Creek Road intersection. - Rumble strips: New sinusoidal edge-line rumble strips are planned for U.S. 360 through Nottoway and adjacent counties. VDOT described these as sinusoidal milled strips that are less jarring to neighbors while still reducing run-off-road crashes.

The VDOT presenter said the county may use tele-fee funds for projects that do not qualify for statewide rural-rustic paving because those projects fall below the 50 vehicles-per-day threshold; supervisors may choose to hard-surface such roads with tele-fee funds if they wish.

Board action: Supervisors gave consensus to advertise the draft secondary six-year plan for a public hearing on May 15; at the May 15 meeting the staff will read the plan into the record and then open the hearing.

Ending: VDOT staff asked board members to identify any routes they would like prioritized before formal programming begins in mid-June, noting that earlier local input reduces deliberation during work sessions and helps VDOT plan funding and right-of-way work.