Wastewater expansion, Cheshire lift station cleaning and Walnut Street stabilization updated to council

3044744 · April 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City engineer reported a preconstruction meeting set for the wastewater treatment plant expansion, televising and cleaning of the Cheshire Ditch sanitary sewer line by FAPE Corp, and a $590,000 Walnut Street creek-stabilization contract with soil nails up to 20 feet; the engineer said the contractor aims to have paving by July 4.

Sunbury's city engineer updated council on three public-works projects April 16: a coming preconstruction meeting for the wastewater treatment plant expansion, sanitary line cleaning tied to the Cheshire Road lift station optimization, and active construction to stabilize the Walnut Street creek bank.

City Engineer Obraske said a preconstruction meeting with contractor Simonson for the wastewater treatment plant expansion is scheduled for the morning of Monday, April 28, at which time the project schedule and major component procurement timelines will be discussed. Obraske also said the city awarded a separate cleaning and televising contract for the Cheshire Ditch sanitary sewer line to FAPE Corp; that work began the week of the meeting and was expected to be completed by the end of that week unless weather caused a short delay.

On the Walnut Street stabilization project, Obraske showed council photographs of ongoing soil‑nail installation used to shore the creek bank. She said the construction contract is approximately $590,000 and that soil‑nail elements of the work involve rebar arms up to 20 feet in length; the next step is applying shotcrete or concrete to the nailing to stabilize the wall. She said the contractor hopes to have the portion of Walnut Street reopened and paved by July 4, subject to progress meetings and schedule checks.

The Cheshire Road lift station project was discussed in reading as an ordinance (second reading) awarding construction; Obraske's work on televising and cleaning the sanitary line is intended to optimize conditions at that location before or during construction. Council did not take final action on the Cheshire Road construction award at this meeting (it remained at second reading).

Clarifying details - Wastewater treatment plant expansion: preconstruction meeting with Simonson scheduled April 28 (morning). - Cheshire Ditch sanitary sewer cleaning: contract awarded to FAPE Corp; cleaning and televising work started the week of April 16 and was expected to finish by end of that week unless delayed. - Walnut Street stabilization: construction contract approximately $590,000; soil nails/rebar arms up to 20 feet; target to have the road segment paved by July 4 pending schedule.

Ending: Engineer Obraske said she would hold regular progress meetings with the contractor and report back to council on schedule confirmation and any delays.