Staff: West Bay pathway redesign and house removals require permits, estimated $200,000

3039686 · April 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff told the council environmental and permitting changes require a redesign of the West Bay pathway and permit work tied to removing houses; staff cited a $200,000 proposal for permitting and design work before demolition can proceed.

City staff told the Port Orchard City Council during its April work study that environmental regulations have forced a redesign of a West Bay pathway and that permits tied to removing several houses will add costs before demolition may proceed.

Staff said the pathway segment along West Bay can no longer be constructed as previously planned (concrete poured atop riprap). Instead, the project must be rebuilt as an elevated boardwalk, which requires redesign and additional permitting for the first phase. Staff reported the permitting and design package for the houses and the boardwalk carries a proposal price of about $200,000 and said the city cannot remove the houses without those permits in place.

The staff presenter said consultants are confident permits can be issued by summer and that the city intends to proceed with the planned house removals once the permitting work is completed. Council members asked whether the estimate covered all design phases; staff said the $200,000 was the proposal for permitting and redesign work and that the contract could come to the council for consideration as soon as the following month.

Staff also said the redesign and permitting will draw on money already budgeted for the pathway activity and related planning contingencies.

Ending: Staff said they will bring a contract for the permitting and design work to the council when arrangements are finalized and that construction sequencing depends on permit approvals.