Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Public Safety Infrastructure topic
No spam. Unsubscribe anytime.
Select Board authorizes $2.5 million bond application and hears fire station construction update
Summary
The West Swanzey Select Board authorized the chair to sign a New Hampshire Municipal Bond Bank application for $2.5 million to help fund a new fire station at 321 Homestead Highway and received a construction progress update and timeline from staff.
Get email alerts on the Public Safety Infrastructure topic
No spam. Unsubscribe anytime.
The West Swanzey Select Board on a voice vote authorized the board chair to sign a New Hampshire Municipal Bond Bank application for a $2,500,000 bond to partially fund construction of a new fire station at 321 Homestead Highway. The motion drew a voice vote of “Aye.”
The board heard a detailed financial briefing on bond-term options and debt-service impacts and a separate construction update covering site work, permitting and schedule. A staff presenter told the board the application had been prepared with a 30-year term but that the town could change the term before the application’s final change date if market conditions moved: “For the purpose of the application…I filled it out with 30 years,” the presenter said, explaining bond-bank timing and deadlines. The presenter said the bond bank holds sales twice a year and that the town was seeking the July sale; he also said the application had a firm-change date near May and that staff would monitor market conditions and report changes back to the board.
Why it matters: The bond application is the financing step the town took to secure loan proceeds for construction. An approved sale would provide cash to proceed with site work and contract awards; the term chosen affects long‑term interest costs and annual debt service paid by taxpayers.
Board discussion focused on how a longer term would affect near‑term tax bills and the town’s overall capital plan. The presenter told the board recent spreads between 20‑ and 30‑year terms were unusually tight — roughly 17 basis points in the model presented — which, he said, favored a longer term for fitting the station’s cost into the town’s forecast. He also noted that some of the town’s current bonds are scheduled to retire soon, which helps the debt-service picture.
On construction, a project manager reported the job started March 31, 2025, and that preliminary on‑site work, including erosion control and topsoil stripping, is underway. Bids for a general contractor were due April 28, 2025; once a contractor is selected the manager said site prep could begin within weeks and a foundation could be ready within about three weeks of starting work. The manager said remaining permitting steps include a clearance from the airport authority (referred to in the meeting as “FHA for the airport”) and other routine municipal approvals; staff indicated they did not expect those to cause a schedule slip but would follow up.
On utilities, staff said they will pursue a flow test of an existing well if architects and site designers agree it can remain; preliminary cost estimates for well testing were reported at $1,500 to $2,000. Design refinements under discussion included using wider foundation walls and an open span in the apparatus bay to reduce future maintenance and possible construction costs.
Next steps: The board authorized staff to file the bond‑bank application and directed staff to continue monitoring bond markets and report back before the application’s final change date if conditions changed. The construction team will review bids, finalize the site plan and complete required tests and permits before large‑scale site work begins.
The board did not record a roll‑call vote with names during the action; the motion was approved by voice.

