DuPage County Transportation Committee approves contracts, amendments and awards for 2025 pavement, equipment and services
Summary
The committee approved multiple renewals and new contracts for fleet repair, parts, guardrails and pavement engineering work; it also approved amendments closing or reducing several prior contracts and awarded 2025 pavement and sidewalk projects to contractors with estimated township and county costs.
Get email alerts on the Procurement And Contracts topic
No spam. Unsubscribe anytime.
The DuPage County Transportation Committee approved a package of procurement items, contract renewals, contract amendments and project awarding resolutions covering fleet repair, parts, guardrail work, construction engineering and 2025 pavement and sidewalk programs.
Committee members combined several procurement requisitions and change orders and then approved a series of contracts and renewals for the transportation division. Approved items included renewal and term contracts for service and parts for diesel trucks and plows; on‑call repair services; Force America parts; refuse and recycling pickup; guardrail installation and repair; Ford parts; and professional construction engineering services for the 2025 pavement maintenance south and north programs.
Notable contract approvals (motion and voice vote): - A contract to Complete Fleet Services Incorporated for service repair and parts for diesel trucks and plows, period 06/01/2025–05/31/2026, contract not to exceed $15,000 (third and final renewal). - A contract to Kevin's Auto and Diesel Repair for on‑call heavy‑duty diesel truck repairs and parts, period 06/01/2025–05/31/2026, contract not to exceed $15,000 (third and final renewal). - A contract to O'Nell Industries Incorporated to furnish Force America parts, period 06/01/2025–05/31/2026, contract not to exceed $25,000 (first of three renewal options). - A contract to Groot Incorporated for refuse disposal and recycling pickup, period 06/01/2025–05/31/2026, contract not to exceed $25,000 (second of three renewal options, bid 2226 FM). - A contract to Northern Contracting Incorporated for guardrail furnish, delivery, repair and installation, period 05/12/2025–04/30/2026, contract not to exceed $75,000. - A contract to Haggerty Ford to furnish Ford Motorcraft repair and replacement parts, period 06/01/2025–05/31/2026, contract not to exceed $100,000 (first of three renewals). - A professional services contract to SiOrba Group Incorporated for construction engineering on the 2025 pavement maintenance south program, period 04/22/2025–06/30/2026, contract not to exceed $4,471,773 (qualification‑based selection stated). - A professional services contract to Premier Engineers Limited for construction engineering on the 2025 pavement maintenance north program, period 04/22/2025–06/30/2026, contract not to exceed $535,843.
The committee also approved extensions and closeouts for several existing purchase orders and contracts, including an extension for American Surveying Engineering for right‑of‑way negotiation services through 05/31/2026; an extended purchase order for Rush Truck Centers of Illinois to deliver eight plow trucks through 11/30/2025 (fiscal year line changes noted); and closing of remaining encumbrances for LTOFA Industries (Caterpillar parts) and AutoTech Centers (Goodyear tires), noting those contracts had expired in 2024.
Amendments to prior resolutions and contracts were approved, primarily decreasing remaining funding and closing contracts for several 2020–2023 programs. The committee approved multiple amendments that reduced county costs for LED traffic signal replacements, intersection improvements with the village of Carol Stream, 2021 sidewalk improvements and multiple township resurfacing and pavement programs. One amendment increased a 2023 pavement maintenance north contract by $150,610.95, resulting in an amended contract total of $6,438,910.95 (an increase of 2.39%), which staff said reflected additional work encountered during closeout.
Awards for 2025 projects approved by voice vote included: - Geneva Construction Company — Winfield Township Liberty Street resurfacing project (estimated township cost $116,579.57; no county cost). - Triggy Construction — 2025 sidewalk improvements program (estimated county cost $985,127.30). - K5 Construction Corporation — 2025 pavement maintenance south program (estimated county cost $7,150,125.82). - Builders Paving LLC — 2025 pavement maintenance north program (estimated county cost $7,524,912.96).
During discussion of contract closeouts and one 2023 increase, committee member Mister Zedd asked why the 2023 pavement maintenance north contract required an increase despite perceived poor performance. A staff member replied that additional, unexpected work — damaged sidewalks, pavement conditions and deteriorated curbs — was identified during construction and that final closeouts and quantity agreements can take time.
All motions described above were approved by voice vote; the meeting record shows “All in favor? Aye.” The committee also approved an intergovernmental agreement (DTR00925) with the Winfield Township Road District for the Liberty Street resurfacing project with no county cost.