Summary of formal votes taken by the Templeton Conservation Commission on April 14, including approval of minutes, two order‑of‑condition extensions, and continuances of two continued NOIs.
Get email alerts on the Meeting Votes topic
No spam. Unsubscribe anytime.
At its April 14, 2025 meeting the Templeton Conservation Commission recorded the following formal actions and outcomes.
- Approval of meeting minutes (Feb. 10, 2025): Motion to approve passed (recorded affirmatives by commissioners present).
- Continued public hearings: The commission reopened and then continued two Notices of Intent to the May conservation meeting: Pages Road NOI (file pending) and 66 Rainbow Drive (NOI for a 20×20 deck in the 50‑ft buffer at Pottersville Pond). Both items were continued at the applicant’s request.
- Extension — Riverside Road bridge project (Order of Conditions 3040376): The commission granted a one‑year extension (new expiration 04/19/2026) to allow the applicant to complete bridge installation. The motion passed and the agent will obtain signatures as needed.
- Extension — Queen Lake Road project (Order of Conditions 3040368): The commission granted a three‑year extension (new expiration 05/19/2028) at the applicant’s request due to financial delays; commissioners noted the order of conditions remains recorded until a Certificate of Compliance matches the approved plans.
- Administrative items: The commission placed the Car Works enforcement order on the May agenda and noted several community cleanup events and the annual railroad herbicide application schedule in agent updates.
Votes above were recorded during the April 14 meeting; details and file numbers are in the commission record.