Board grants 18‑month extension for USS Hilltop Solar project; developer cites permitting and PPA delays

2997359 · April 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Supervisors approved an extension modifying the construction start and completion dates for a proposed 3.3 MW Hilltop solar facility, after the developer described longer lead times for equipment and a pending power‑purchase agreement (PPA) with Dominion Energy.

The Rockbridge County Board of Supervisors on April 14 approved an amendment to the special-exception permit for USS Hilltop Solar LLC, extending the required construction-start and project-completion deadlines for a proposed roughly 3.3‑megawatt AC solar facility on Loitally Road in Natural Bridge Station.

County staff presented the applicant’s request to amend condition 9 of the January 2024 special-exception permit, which originally required implementation by May 1, 2025 and completion by Dec. 31, 2025. The planning commission recommended revision to require construction to…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans