El Campo awards Town and Country street reconstruction to Matagorda Construction for up to $3.19 million

2985956 · April 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved Resolution R2025-23 awarding the Town and Country Neighborhood reconstruction Phase 1 to Matagorda Construction and Materials for an amount not to exceed $3,191,537 after rebidding and scope adjustments that removed a utility component and lowered costs.

The El Campo City Council on its April 2025 meeting awarded the Town and Country Neighborhood Street Reconstruction Phase 1 contract to Matagorda Construction and Materials in an amount not to exceed $3,191,537, authorizing the city manager or designee to execute related documents.

City staff and the project engineer said the project’s original low bid had been $5,441,118; staff and the council then rejected initial bids and re-scoped the contract, removing a utility component and adjusting storm-sewer specifications to allow more competitive bidding. The re-scope reduced the project cost and brought it within the city’s available funding.

Engineer Brian Greer of Quiddity (in the audience) and staff explained that the revised scope included drainage and road reconstruction for Phase 1 and that Phase 2 would cover additional streets (for example Myatt and Wallace). Greer said the main technical change was in storm-sewer design and that bid alternates included options such as concrete versus plastic pipe; staff said some drainage segments are out of the travel way and can use different pipe standards.

Council members praised the approach that cut costs. One council member said the shift saved taxpayers nearly $2.5 million compared with the earlier low bid. Council members also asked staff to present the utility improvements and full project accounting at an upcoming meeting so the council could see how the overall program fits the adopted budget.

A motion to award the contract to Matagorda Construction was moved and seconded; the motion carried. The transcript records the motion passed but does not record a roll-call tally.

Staff noted Matagorda Construction was unable to attend the meeting due to a family emergency but was vetted by the city engineer. The contract is to proceed under the revised Phase 1 scope; staff will return with additional budget details, including utility improvements and prior pre-paid engineering charges, for council review.