Council approves advertisement for 2025 pavement rehabilitation bids, engineer estimates $1.48 million
Summary
City engineer presented a $1,476,071.82 estimate for the 2025 pavement rehabilitation program; council approved authorization to advertise, with bids to be opened April 22.
Get email alerts on the Pavement Rehabilitation topic
No spam. Unsubscribe anytime.
Seven Hills City Council authorized the city to advertise for bids for the 2025 pavement rehabilitation program after City Engineer Gerson presented an engineer’s estimate of $1,476,071.82.
Gerson said, if passed, the city would advertise on April 3 and April 10 and open bids on April 22 at 10:30 a.m. The council voted to authorize advertising; if bids are in order, staff will return with a recommendation at a subsequent council meeting after the bid opening.
The engineer said the city would review bid results and provide a recommendation to council. The meeting record did not include a detailed scope of work or funding source breakdown for the project; those details are to be provided with the bid documents and staff recommendation.