Committee approves multiple infrastructure contracts, renewals and purchases by consent

2777666 · March 26, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Columbia County Public Works committee approved a package of consent items including SCADA upgrades, sewer and sewer trunk change orders, fence repairs and road improvements; staff recommended approval for each item and the committee passed them by consent.

The Columbia County Public Works and Engineering Services Committee approved a package of consent items on March 25 covering system upgrades, construction change orders, consultant agreements and equipment purchases.

Key items approved by consent included a SCADA system upgrade contract recommendation with Southern Flow for an initial cost of $610,820; staff said the county expects to average about $90,000 in annual savings over 10 years from the system replacement and to gain cybersecurity features such as two-factor authentication. Mr. Gordon presented that item and staff recommended approval.

Other consent approvals included a deductive change order with RCN Contracting for the sheriff’s repair garage (staff said allowances were being cleared and the project came in on budget), an independent-contractor agreement with Blue Water Engineering Services to perform erosion-control and post-rain monitoring for the Uchee Creek (Oochy/Uchee) Force Main for under $10,000, and a contract renewal with Goodwyn Mills & Caywood for periodic hydraulic model maintenance for $18,000 (July 1–June 30 term).

The committee also approved a Crawford Creek sewer trunk line replacement change order totaling $577,101.91; staff said unanticipated rock and extended bypass pumping drove the cost increase. An independent-contractor award to N and P Fence for $85,791 to repair security fencing at the Re Creek plant was approved; staff noted clearing/trees increased the cost and that the county would seek BEMA reimbursement and insurance where applicable.

The committee approved the purchase of 39 emergency-vehicle preemption modules (sometimes called preemption or vehicle control units) for $124,410 to equip the remaining fire/rescue fleet. A bid and contract with Jay Long to install a mini-roundabout at General Wood Parkway and Riverwood Parkway for $569,884.14 (four-month completion estimate) was approved and staff said it would be funded from SPLOST funds.

A consultant agreement with Cranston Engineering for design services on the Watson Bailey Road improvement project was approved for $81,580; staff estimated construction costs around $2,000,000 and said the funding source would be returned to the board at a later date (the independent-contractor agreement itself was approved by consent while the project funding decision was deferred). The committee also approved a one-year, time-and-materials agreement with Goodwyn Mills & Caywood to provide MPO consulting support at up to $5,000 per month (total $60,000) to help the county pursue federal MPO funding and Transportation Improvement Plan opportunities.

Finally, the committee accepted as-completed improvements from Blackstone Development Company (sewer utility relocation in River Island) and accepted improvements for Tillery Park South including roads, storm, water and sewer systems plus associated rights-of-way and easements.

Votes at a glance

- SCADA upgrade (Southern Flow): recommended $610,820 — approved by consent - RCN Contracting deductive change order (sheriff’s repair garage): approved by consent — amount not specified in transcript - MB Con final change order (two water treatment plants): sent to debate (see separate item) - Blue Water Engineering Services (Uchee Creek monitoring): approved by consent — estimated under $10,000 - Goodwyn Mills & Caywood hydraulic model renewal: $18,000 — approved by consent - Crawford Creek sewer trunk change order: $577,101.91 — approved by consent - N and P Fence (Re Creek plant fence repair): $85,791 — approved by consent; staff will seek BEMA/insurance reimbursement - Emergency vehicle preemption modules (39 units): $124,410 — approved by consent - Mini roundabout (Jay Long): $569,884.14 — approved by consent; four-month completion estimate; SPLOST funding - Watson Bailey Road consultant agreement (Cranston Engineering): $81,580 — approved by consent; construction funding source to be identified later - MPO consulting (Goodwyn Mills & Caywood): $5,000/month, up to $60,000/year — approved by consent - Acceptance of Blackstone Development improvements (River Island sewer relocation): approved by consent - Acceptance of Tillery Park South improvements (roads, storm, water, sewer, ROWs/easements): approved by consent - Proclamation: April as Safe Digging Month in Columbia County — approved by consent

Committee members moved the consent package and multiple items carried with "So moved" recorded in the transcript; the MB Con closeout was removed from consent and moved to debate for additional committee consideration.