Sanitation district reports $30 million secondary clarifier finished; start-up and biology introduction underway
Summary
A council member reported the secondary clarifier project for the sanitation district is complete and filled; start-up activities and biological seeding are underway and the $30 million project came in under budget to ratepayers despite later delays not attributable to the project team.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
During council reports, a member of the Arroyo Grande City Council said the sanitation district's new secondary clarifier is complete and currently full while staff "putting biology in there" as part of the start-up process.
The council member described the project as a $30,000,000 effort that largely went according to plan, although the speaker noted there had been a subsequent delay that the speaker said was "no fault of anyone" and that the delay incurred no additional cost to ratepayers.
No formal council action was required; the item was presented as an informational update during council reports. Staff did not provide a detailed schedule for when the clarifier will enter full service, but the council member said they expect to report progress in the following month.