District facilities staff described progress on a school construction project, including roof decking, second-story slabs, structural floors and utility piers; an initial drone flight and framing work were cited.

District facilities staff briefed trustees on ongoing construction at a campus expansion. Staff said the north wing framing was nearly complete, decking was in place on the roof above the administration wing, and second-floor slabs and interior walls were under construction.

Officials described completion of piers, initial mud slabs and work on the structural floor. The facilities update referenced a preliminary drone video flight and noted efforts to keep the new footprint economical while matching existing campus dimensions where possible.

A trustee asked an operational question about access and single-door entry points; staff replied that the observation was noted and would be considered during finishing stages. No contract changes, budget amendments or formal votes were recorded in the transcript.

The facilities update was presented as an informational report; staff did not request action from the board in the portion of the transcript provided.