County schedules bids for Garlock Road fish-passage work and advances Delameter culvert design with PBS Engineering

2767291 · March 26, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works put a Garlock Road fish-passage construction call for bids on the consent agenda and presented a consultant agreement with PBS Engineering for Delameter Road culvert replacement; both items are funded largely with grant dollars and are intended to open salmon habitat.

Cowlitz County Public Works announced two fish-passage projects to commissioners: a call for construction bids for the Garlock Road Delameter Creek fish-passage project and a consultant agreement to design replacement culverts on Delameter Road.

County Engineer Susan Eugenis said both items were placed on the consent agenda because she would appear online from a conference rather than in person. She described the Garlock Road project as an estimated $2,000,000 engineering estimate that will open roughly 2.5 miles of habitat and will require closing Garlock Road to through traffic during construction; local access will be maintained at either end of the work zone.

“People will still have access. It's just a little different,” Eugenis said, noting the work is constrained by fish-window timing for in-water work and estimating a likely closure in the range of 60 to 80 days, with final duration to be provided by the engineer.

Eugenis also presented a negotiated consultant agreement with PBS Engineering for design on the Delameter Road culvert-replacement project. She said the contract amount for engineering services is $843,071 and that the overall project is estimated at nearly $7,000,000. Both projects are funded with state and grant money (Eugenis said the Garlock project is funded about 85 percent by the Brian Abbott Fishery restoration program/proceeding grant).

Eugenis explained the design approach: replacing undersized box culverts with structures that incorporate a simulated stream channel through the culvert so juvenile fish can migrate year-round. She said simulated stream channels are added where bedrock does not form a natural channel and that the design will generally extend beyond the roadway to tie into the natural stream bed.

The consultant-selection process followed state procurement rules for architects/engineers: the county issued a request for qualifications, interviewed top firms, and negotiated price after ranking qualifications. The contract will use WSDOT form terms and include disadvantaged-business-enterprise (DBE) participation in accordance with the state contract requirement.

Why this matters: both projects are intended to remove fish barriers and restore salmon access to upstream habitat; the county’s capital program and grant commitments are driving road closures and multi-million-dollar construction planning.

Public Works said it will provide commissioners with the engineer’s estimated closure duration and additional specification details on request.