Board approves CTE electrical change order, awards fence contract and green-energy tests
Summary
The Henderson County board approved a $20,007.27 change order for the CTE addition after contractors encountered an electrical duct bank, awarded a $281,300 fence replacement contract to Cornerstone Fencing, approved a geothermal test-well award, and authorized an RFP-based architect study to estimate future project costs.
Get email alerts on the School Facilities Projects topic
No spam. Unsubscribe anytime.
The Henderson County Board of Education on Feb. 17 approved several facility-related actions: a change order for the Career and Technical Education (CTE) addition, acceptance of a low bid for a district-wide fence replacement, authorization to perform geothermal test wells for South Middle School and selection of an architect to provide opinion-of-probable-cost studies for future projects.
The board approved a proposed CTE change order of $20,007.27 to address an electrical disconnect and to reroute electrical wiring found under a concrete slab. Mister Thomas presented the issue, describing two components: replacement of an electrical panel (just under $7,000) and rerouting conduit to move wiring out of the slab. Doctor Lawson recommended board approval; Mister Alves moved and Miss Williams seconded the motion, which passed by unanimous voice vote.
The board also accepted the low bid for a fence replacement project from Cornerstone Fencing for $281,300, a figure the presenter said was below the budget authorized on the district's BG-1 document. The board approved a revised BG-1 and the owner-contractor contract and directed staff to authorize work to proceed.
For the South Middle School geothermal work, the board approved award of the test well and conductivity testing to Durban Geothermal, the engineer-recommended bidder; Doctor Lawson had recommended the award and the motion passed unanimously.
Finally, the board approved issuing an RFP-based architectural services engagement with Ross Durant to provide conceptual designs and opinions of probable cost for a list of potential projects the district is studying. Doctor Lawson and Mister Thompson described the work as an early diagnostic step (basic floor plans and elevation sketches, not full MEP design), to be followed by negotiated fees if the district advances any project into design and bid phases.
Why it matters: these actions keep several capital projects on schedule: the CTE addition required a change order to maintain progress, the fence contract will address multiple campus locations, geothermal testing positions the district for potential ground-source HVAC work, and the architect study will give the district cost estimates to inform future bond or project decisions.
Decisions and next steps: contractors were directed to proceed once contracts and permits are in place; the architect engagement is to be negotiated following award; geothermal test results will be used for later design and bid packages.
All facility motions recorded in the minutes passed by unanimous voice vote; the transcript does not record individual roll-call tallies.