Frog Pond contractor selected by surety; AT Creek contract terminated as district works with surety
Summary
District staff said the Frog Pond project is restarting after the surety selected a general contractor; AT Creek Middle School remains in transition after contract termination as the district and surety coordinate next steps.
District operations staff told the school board that work on two bond projects is moving forward under surety oversight after earlier contractor terminations.
Pat McGuff, operations staff, said Zurich, the district's bonding company, has "selected a general contractor that is agreeable to the district" for the Frog Pond project and that activity would begin to ramp up near spring…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat