Bullitt County board hears construction update; March 1 set as substantial completion for multiple athletic projects
Summary
Studio Kramer architect Kate Noble Ward told the Bullitt County Board of Education at its February meeting that contract extensions and change orders put multiple athletic fields and associated work on track for a March 1 substantial completion, with several contract transfers and credits reducing net cost impacts.
At its February meeting, the Bullitt County Board of Education received a construction update from Kate Noble Ward of Studio Kramer Architects, who said Calhoun Construction and the Motes Group received 14-calendar-day extensions that set a new substantial completion date of March 1 for key turf and field work.
Ward told the board the extensions were granted after a site visit and weather review and that the extension for Calhoun avoided liquidated damages. “We felt it was valid to extend Calhoun's contract by another 14 calendar days with a new substantial completion date of March 1,” Ward said.
The update covered multiple sites. Ward said Bullitt Central’s field work is sufficiently advanced that both baseball and softball teams can use the field; backstop netting was finished, and lighting and AV testing is planned in the coming weeks. At Bullitt East she reported all turf is down for the baseball field and that access points…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat