Summary

The Streator City Council unanimously approved an intergovernmental agreement with the Illinois Department of Transportation to allow bidding and move forward with the Iowa Avenue Reconstruction Project, which includes continuous sidewalks and a mix of concrete base with asphalt overlay.

The Streator City Council on an unspecified date approved an intergovernmental agreement with the Illinois Department of Transportation to allow the Iowa Avenue Reconstruction Project to proceed to bid and to accept state-administered funds for construction.

City staff told the council the project is scheduled to be bid in Springfield in two days; passage of the agreement allows the city's portion to be appropriated so construction can proceed. The project includes continuous sidewalks from Main Street to Johnson, a phased construction approach and a pavement design that widens existing concrete bases and places an asphalt overlay in most areas.

The council's approval was made by motion from Steve Connor, seconded by Tim Carey, and passed on a roll call with all members recorded as voting in the affirmative.

The staff presentation said the project will be constructed in phases from Main to Kent, then through the truck-dock area and around to Johnson, and that on parts of the corridor there is an existing concrete pavement 8 to 14 inches thick; city crews will widen those concrete bases to a full 24-foot width and place an asphalt surface over them. The staff member noted, “The project is actually bidding in Springfield on Friday,” and described the sidewalk locations as following the east side of the street from Main and then switching to the west side for the final block near Bronson, with crosswalks at the transition.

According to the presentation, approximately $750,000 of the project funding came from congressional-directed funds identified as from Darren Lippert's office. Staff said the state pays project bills and that the city may not receive invoices until construction is complete; on previous projects the city was not billed until 2026. The presentation did not specify the city's total share or a final construction schedule beyond the bid date.

Why it matters: The project rebuilds an arterial street in Streator and adds continuous pedestrian access on Iowa Avenue, which the city described as intended to improve safety and connectivity. The agreement with IDOT is a prerequisite to contract award and state oversight of construction.

Votes at the meeting: Motion to accept and authorize execution of the intergovernmental agreement with the Illinois Department of Transportation to construct the Iowa Avenue Reconstruction Project — mover: Steve Connor; seconder: Tim Carey; outcome: approved (recorded roll-call votes: Connor, Gary, McMullen, Reid, Gary Veevak recorded as Aye).