SDG&E reports large reduction in zeros, plans public ICA access and downloadable files

2623179 ยท March 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

San Diego Gas & Electric told the CPUC workshop it has substantially reduced the share of ICA nodes reporting zero hosting capacity through data-validation work and will remove login requirements for its ICA portal; SDG&E also plans downloadable limited generation profile files and further portal refinements.

San Diego Gas & Electric reported progress on ICA data validation and said it has materially reduced the portion of nodes showing zero available hosting capacity by applying rigorous QA/QC and remediation workflows.

SDG&E principal engineer Katerina Vargas said the utility follows the same ICA methodology used by other IOUs โ€” a node-by-node analysis using 576-hour profiles and iterative load-flow runs against multiple technical study criteria โ€” and reiterated the company's monthly-update cadence. SDG&E described a data-validation program that reviews circuits reporting zeros to identify root causes and correct data or modeling issues before publication.

SDG&E said it has reduced the share of nodes with zero ICA results from double-digit percentages in prior years to 8.5% (as of the December 2024 dataset the company presented). The utility also reported that at the circuit level, most circuits show some available capacity at some hour; SDG&E uses circuit-average distributions to prioritize remediation of potentially false zeros.

On portal changes and accessibility: SDG&E said users will no longer require login credentials to view the ICA portal beginning in March (the utility described that change as intended to broaden access while ensuring back-end data protections). SDG&E plans to publish downloadable limited generation profile (LGP) templates (a standardized format) and to migrate forthcoming refinements into production; SDG&E indicated an LGP availability target around July 10 for downloadable files.

On Rule 21 and privacy: SDG&E explained it treats "15/15" privacy-sensitive circuits (those with fewer than 15 customers or a single customer representing more than 15% of circuit load) differently; the utility said it does not publish ICA results for circuits that meet the 15/15 threshold on the public map but that it uses those results internally during interconnection screening so applicants still receive project-specific engineering determinations.

Stakeholders asked SDG&E to explain how the 15/15 rule is applied in practice and whether SDG&E removes only load-level data (OpFlex/load layers) or removes broader circuit-level outputs. SDG&E said it would confirm specific presentation details and report back.

Ending: SDG&E said its data-validation work reduced zeros to about 8.5% of nodes and that it will expand portal access and downloadable data to give developers more tools while continuing to refine the ICA methodology.