Commission approves NESEUS light-industrial development amid traffic and wetland-impact concerns
Summary
Commission approved a major development order for a multi-building light-industrial/warehouse project on County Highway 393 (MAJ24-000004). Staff said technical comments were resolved; traffic, wetlands and mobility-fee issues drew extended discussion and one commissioner voted no.
Get email alerts on the Major Development Order topic
No spam. Unsubscribe anytime.
The Walton County Planning Commission approved a major development order (MAJ24-000004) for a proposed light-industrial/warehouse complex on County Highway 393 after staff said all technical-review comments had been addressed. The approval passed with one dissenting vote.
Project and staff review: Kelly Schulz, planning staff, said the application proposes multiple warehouse/office buildings (five 2,400-square-foot buildings plus an existing 4,423-square-foot storage area and an existing 423-square-foot warehouse), and noted the project was reviewed under the county’s mobility-fee ordinance; the mobility fee will be assessed at building-permit review. Schulz said the technical-review committee placed several conditions the applicant addressed and that staff recommends approval subject to conditions.
Traffic and capacity issues: Commissioners pressed staff and the applicant on traffic impacts to County Road 393 and the nearby SR 98/393 intersection. The county’s traffic-review letter estimated the project would generate about 48 PM peak-hour trips (10 entering, 38 exiting) based on ITE trip-generation rates for the theoretical maximum build-out; the county’s reviewer concluded the trips would not create a significant adverse impact but flagged that the analysis used a maximum-intensity scenario. Commissioner comments and public discussion raised concern that existing peak-hour congestion on 393 and at nearby intersections could produce operational or safety impacts when the project builds out.
Applicant response: Dean Burgess, the engineer of record with Emerald Coast Associates, described the proposal as aimed at trade and service businesses (for example, electricians, carpenters and a pool-builder tenant expressing interest) rather than high-trip commercial or large-distribution uses. Burgess said the development’s parking and layout were sized to meet county code and that the site preserves wetlands where possible; he acknowledged the project will impact some wetlands and said the design applies the county’s impervious-surface penalty for wetland impacts. "The amount of people per building is limited to probably 5 or 6 people," Burgess said, describing expected staffing and trip generation.
Wetlands and stormwater: The applicant’s engineer said existing wetlands total about 3.25 acres, with 2.56 acres of wetland impacts proposed; the project’s calculated floor-area ratio was about 30 percent and required parking counts exceed code minimums (70 provided vs. 66 required). Staff said federal and state wetland permits are not required to obtain the development order but must be in hand before construction starts; the county will require proof of any required permits at the preconstruction meeting.
Outcome: The commission approved the major-development order on a recorded voice vote; one commissioner voted against the motion. Conditions in staff’s recommended order address mobility-fee payment at permit review, required permits, and standard site-plan and stormwater conditions.