Council selects generator vendor for main lift station; staff discussed sizing and warranty needs
Summary
Council discussed two generator bids and directed staff to proceed with the lower-cost vendor; the chosen unit carries a lead time of about 12 weeks and staff emphasized using a licensed installer to preserve warranty.
Get email alerts on the Public Infrastructure topic
No spam. Unsubscribe anytime.
The council reviewed competing quotes for a standby generator for the town’s main lift station and indicated a vendor selection to proceed based on price and compatibility with the lift station’s electrical load.
Two bids were discussed: a larger 35 kW commercial unit and a smaller ~32 kW unit offered at a lower price by a vendor described in the packet as the generator superstore. Council members noted differences in the concrete pad and transfer-switch pricing across quotes and discussed the horsepower and startup loads for the lift-station pumps. Staff said the 32 kW option is intended for smaller projects and that warranty preservation requires a licensed installer.
The council concluded that the lower-price vendor (listed in the meeting packet as the generator superstore) provided a suitable quote within grant budget constraints; council members noted the town’s grant balance of roughly $42,000 and that the selected unit fit within that remaining amount. Staff said the selected generator has an approximately 12‑week lead time, and the town will coordinate installation details, transfer switch pricing, and licensed installer requirements to preserve warranty coverage. No construction contract was signed at the meeting; staff will finalize purchase and installation agreements and report back.