County awards Bridal 155 contract, readies two Community Crossings applications

2596581 · January 9, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Adams County's highway engineer recommended and the commissioners approved awarding Bridal 155 to Grumbaugh Construction at $295,000 and authorized staff to finalize two Community Crossings grant applications (Bridge 180 and 300 North overlay).

Adams County commissioners approved awarding the Bridal 155 rehabilitation contract to Grumbaugh Construction of Arcanum, Ohio, after a December bid opening and accepted the county highway engineer’s recommendation.

Nate Rubschlag, Adams County highway engineer, told commissioners Grumbaugh submitted the apparent low bid of $295,000 for the Bridal 155 project. Commissioners approved the award and signed contract documents at the meeting so the county can proceed; the engineer said the county expects to secure 75% funding through the Community Crossings program and will turn in final application materials before the Jan. 31 deadline.

Rubschlag also updated commissioners on two Community Crossings applications being finalized for 2025: Bridge 180 (intersection of 825 S. and 650 W.) and an asphalt overlay with minor structural work on 300 North from U.S. 27 to the western county line. The engineer said the state’s first-call allocation for the program this year is $1.5 million and that the county is submitting both projects to maximize its chances for funding. No further action was required on the grant submissions during the meeting; staff will finalize and submit the applications by Jan. 31.

Why it matters: the contract award moves a county bridge/road project into construction and the Community Crossings submissions set the county up to obtain state matching funds for two additional projects; timelines for construction and state awards were discussed.

Quotes: "Grumbaugh was the apparent low and is the low bidder, at $295,000 on that project," Nate Rubschlag said during the meeting. The board then moved, seconded and approved signing the contract documents.

Next steps: Highway staff will submit final Community Crossings application packets by the Jan. 31 deadline and will oversee contract award execution and coordination with the contractor.